|
| |

|
On
the Construction of
Soil Bentonite Radon Barriers
Proceedings
of the Second International Conference
on Tailings & Mine Waste '95
Fort
Collins, Colorado, USA
January 17-20, 1995
Bill
Frame Jr.
Gears,
Inc., Crested Butte, CO., USA
Tom
Webber
Pyramid
Environmental, Inc., Greensboro, NC, USA
ABSTRACT:
This paper will present case histories on two separate soil
bentonite radon barrier cover projects. The paper will discuss the
constraints, specific demands, problems and solutions involved in the
construction of each project. Since the paper is being presented by two
contractors, it will detail the hands on approach used to successfully
complete these projects.
|
|
Introduction
Components
& Specs
Mixing
Process
Case
Histories
Summary |
I
Introduction
Gears.
Inc. (Gears) and its' sister company Pyramid Environmental, Inc. (PEI) are
construction companies based in Colorado and North Carolina. Both
companies specialize in the mixing of materials that require a high degree
of accuracy.
As
part of the U.S. Department of Energy's (DOE) Uranium Mill Tailings
Remedial Action (UMTRA) Project, work is being done at two sites in
Colorado. These two sites are located in Gunnison and Rifle. These two
projects involved the construction ofa cell in which the mill tailings are
stored. A part of the construction of these cells involves the mixing and
placing of bentonite amended soil radon barriers.
Gears
was contracted by Ames Construction (Ames) to mix approximately 41,000 CY
of radon barrier material for the Gunnison site. This project was
completed in July of 1995. PEI was contracted by Green International, Inc.
(Green) to mix approximately 125,000 CY of radon barrier material for the
Rifle site. This project is anticipated to be completed by November 15,
1995.
|
|
Components
& Specs
Mixing
Process
Case
Histories
Summary |
|
II
Components and Specifications
Soil,
Bentonite and water are the three components of soil-bentonite. Soil is
the major building block of the soil-bentonite. One of the first quality
control items necessary to obtain is the consistency of gradation. If the
material is not consistent, it will be more difficult to determine the
percentage of bentonite necessary to obtain the required permeability.
Other important items requiring consideration are: moisture content,
percentage of silt and percentage of clay.
Bentonite
is a naturally occurring clay comprised primarily of the mineral
montmorillonite, whose unique crystalline structure is responsible for the
clay's properties. The clay structure, when dry, resembles a
negatively-charged stack of plates. When the plates come in contact with a
polar liquid such as water, the plates absorb the liquid forcing them
apart and this is the mechanism by which bentonite seals soil.
Water
is the component that makes the bentonite swell and although very
important, is often taken for granted. As a general rule only potable
water should be used.
MX-Ferguson
Company (MK) was the DOE's contractor for both the Gunnison and Rifle
sites. MK prepared the specifications for the radon barrier for both
projects. The Gunnison project specified a soil bentonite utilizing 5% dry
bentonite to dry soil. The bentonite specified was an untreated sodium
bentonite, Envirogel 200 as manufactured by Wyo-Ben, Inc., or approved
equal.
The
soil was obtained from an on site borrow source. This soil had to meet the
following specifications, soil with 95% finer than 1 inch, a minimum of
50% passing the No.200 sieve and contain not more than one percent of
organic material. The water was obtained from an on site well.
The
Rifle project specified a soil bentonite utilizing 4% dry bentonite to dry
soil. The bentonite specified was a Wyoming sodium bentonite as obtained
from H&H Bentonite, Grand Junction, Colorado, or an approved equal.
The
soil was obtained during the excavation of the cell. This material had to
meet the following specifications, soil with 95% finer than 1 inch with a
maximum size of 3 inches, a minimum of 60% passing the No.200 sieve and
contain not more than one percent by volume of organic matter. The water
was obtained from a local municipal source and trucked to the site.
|
|
Introduction
Mixing
Process
Case
Histories
Summary |
|
III
Mixing Process
Both
Gears and PEI utilize Aran Mixing Plants which are continuous mix,
volumetric, self erecting and self contained units which are state of the
art. The Aran Plants are an Australian made pugmill having manufacturer's
rated capacities between 75 and 1,000 Tons Per Hour (TPH) of continuous
operation contingent upon the engineering properties of the soil material
being used.
During
calibration, a relationship between belt speed and throughput, in tons per
hour, is established. This relationship is linear and is calculated and
recorded by the Contrec model 405 flow computer. This microprocessor based
instrument is flilly programmable. All calculation constants are set via
the front panel switches and are stored permanently in a non-volatile
memory.
The
soil is loaded into the plant's aggregate hopper, the soil is then fed to
the twin shaft mixing chamber on a belt. The flow of soil is controlled by
the operator who programs the Contrec Flow Computer. The bentonite is
stored in the plant's 45 ton silo and fed to the mixing chamber via a
cleated belt which is hydraulic driven via a chain reduction. Water is
metered by means of hydraulically driven constant displacement pumps which
have speed variation via a flow control valve.
|
|
Introduction
Components
& Specs
Case
Histories
Summary |
|
IV
Case Histories
For
the Gunnison project, Ames elected to stage the processing area adjacent
to the cell. Ames excavated and hauled the soil material from the on site
borrow using bellydumps. Ames selected a Powerscreen MK II unit and a
Powerscreen Commander unit in order to try to meet the anticipated
production levels of the two Alan plants. Gears provided an Alan ASR 400 E
and an Alan ASR 280 B with respective anticipated production levels of 300
and 200 TPH each. In addition to the two plants' silos, two horizontal
storage units with 150 ton capacities were brought on site.
The
bentonite for this project was provided by Wyo-Ben, Inc. of Billings, MT.
The bentonite was railed from Greybull, WY to Commerce City, CO. by
Burlington Northern. The bentonite was then transloaded and trucked to the
Gunnison site by Don Ward Trucking. Due to scheduling problems, Ames
elected to truck direct the last 500 tons of bentonite. During peak
production, the two units produced approximately 500 TPH and used 225-250
tons of bentonite per day. On site storage capacity was a problem that
limited production on several occasions.
The
soil material had been pre-wet at the borrow site during the fall of 1994.
The material was close to optimum which was advantageous to the mixing
process but did cause the screening operation problems. In hopes of
decreasing processing quantities, Ames brought in a CMI rototiller to work
the oversize clods prior to screening. This piece of equipment definitely
aided the screening operation but it was an unforeseen expense.
The
soil was screened and then fed directly to the Alan plants where the soil,
bentonite and water were mixed to a homogenous product with 5.1% to 5.4%
bentonite and 20-22% moisture. The mixed soil bentonite was then loaded in
to belly dumps and hauled and spread on the cell in three six inch lifts.
Ames utilized a sheepsfoot roller to spread and compact the soil
bentonite. A laser guided motor grader was utilized to blue top the final
lift.
The
Rifle project's soil was stockpiled at the processing area during the
excavation of the cell. PEI was responsible for screening and mixing,
Green hauled, placed and compacted the soil bentonite. PEI selected an El
Jay 6' X 20' screen deck to screen the soil for both the 400 and 280
plants which fed to a single surge bin, this setup enabled PEI to screen
and mix up to 750 TPH.
The
bentonite for this project was provided by H&H Bentonite of Laramie,
WY. and was trucked direct by Trimac, Inc.. PEI and Green procured 5
horizontal storage units with a total on site capacity of 750-800 tons.
During peak production, PEI was using 200-225 tons per day six days per
week. Due to loading and trucking restrictions deliveries occurred 24
hours per day while mixing was done 10 hours per day.
The
soil material had been stockpiled using scrapers approximately 2 years
prior. The soil had a moisture content of between 6 and 9% which aided the
screening process considerably. The soil was screened and fed directly to
the Alan plants where the soil, bentonite and water were mixed to a
homogenous product with 4.5% bentonite and 18-19.5% moisture. The mixed
soil bentonite was then loaded into scrapers which hauled and placed the
material on the cell in two six inch lifts. Green utilized a D8 dozer to
spread and a sheepsfoot roller to compact the soil bentonite.
|
|
Introduction
Components
& Specs
Mixing
Process
Summary |
|
V
Summary
Problems
and challenges encountered on both projects were the scheduling of
bentonite deliveries, matching screening capacities with mixing
capacities, coordinating mixing operations to match placement capacities
and meeting DOE and MK safety and quality control specifications.
The
Gunnison project did not have sufficient on site bentonite storage but the
two independent screening and mixing units was a plus. The Rifle project
had adequate on site storage and the larger screen and surge bin enabled
higher productions but the units operating as one caused problems. Both
projects utilized a single shift for both mixing and placement and
scheduled required downtime around lunch breaks.
A
key challenge on both projects was the ability to train and equip
personnel to meet the strict safety guidelines enforced by MK. Some safety
regulations although serving a critically important purpose, safety, made
some necessary operating procedures nearly impossible to accomplish. A few
regulations had to be interpreted and implemented as policy in a manner
that provided a safe work place but also enabled the work to be completed
in a timely and cost efficient way.
Another
challenge was the DOE's request that MK's Quality Control (QC) verify' the
bentonite application rate on a weekly basis. Since the Alan plant is a
continuous mix plant, there was no simple way to verify' the application
rate using a small sample. The method that was selected had a degree of
inaccuracy but it enabled QC to verify the application rate. A small
sample of bentonite was run out, timed and weighed, then a sample of soil
was run out, timed and weighed. QC then backed out the moisture
percentages and converted the weights to TPH and determined the
application rate. The problems with these tests were the small sample
size, possible human error in operating the stop watch and the manual
controls and the basic mechanics of the Alan plant. Gears, PEI and QC were
able to verify' the Alan plants accuracy during the calibration process,
when larger samples were run out and compared. During construction the use
of run out tests, the close recording of physical inventories and the use
of the Ramsey scale on the outgoing conveyor reinforced a high level of
confidence in the Alan metering system.
Due
to the Alan plants consistent accuracy and the experience of both Gears'
and PEI's employees and the cooperation of all those involved, both
projects were completed successfully. Teamwork and constant communication
was the key to both projects. |
|
Introduction
Components
& Specs
Mixing
Process
Case
Histories
|
|