Gears, Inc and PEI have been involved in mixing and mixing/placing cement treated base on the following projects.

Project: Capitol City Airport
Location: Lansing, MI    USA
Owner: Capitol City Airport
Engineer: Michigan Dept of Transportation
Contractor: Pappas Brothers Construction 
Construction: June, 2001 - July, 2001
Tons Mixed: 5,211
Description: Mixed Cement treated base for the replacement of the Runway apron at the capitol city airport
Project: Kingman Hwy Deluge Wash
Location: Kingman, AZ    USA
Owner: ADOT
Engineer: ADOT
Contractor: FNF Construction, Inc.
Construction: April, 2011 - May, 2011
Tons Mixed: 12,461
Description: CSA mixing for ADOT project Kingman Hwy 93
Project: Kingman Hwy Deluge Wash Phase 2
Location: Kingman, AZ    USA
Owner: ADOT
Engineer: ADOT
Contractor: FNF Construction, Inc.
Construction: January, 2012 - February, 2012
Tons Mixed: 9,358
Description: CSA mixing for ADOT project Kingman Hwy 93 - Phase 2